How Long Does Interior Design Take in Pune
Design Process

How Long Does Interior Design Take in Pune

20 June 2026 · 7 min read

Quick Answer

A complete 2 BHK interior design project in Pune takes 12–18 weeks from first call to final handover. Design phase: 3–5 weeks (renders + material approval). Execution: 10–14 weeks. The biggest driver of delay is not the contractor — it's starting construction before the design is fully approved.


The Realistic Week-by-Week Timeline

Weeks 1–2: Discovery and Brief

Ali visits your flat, reviews the floor plan, and understands your brief, budget, and timeline. A hand-drawn concept sketch is produced at the first visit. No design work begins until the brief is clear and agreed.

Weeks 2–5: 3D Design and Approval

Photorealistic 3D renders for every key room — living, kitchen, master bedroom, bathrooms. This takes 2–3 weeks from brief sign-off. One revision round is included. Work does not begin until renders are approved. This step is the single biggest protection against mid-project changes.

Weeks 3–6: Material Selection and BOQ

In parallel with 3D design: tile selections, paint choices, hardware, flooring, and fabric are finalised. Vendor quotations are gathered. A full bill of quantities is produced and approved. Total project cost is confirmed before any work begins.

Weeks 5–9: Civil Work

Demolition (where needed), waterproofing, tile work (flooring and bathrooms), basic electrical conduit rough-in. In a new-possession flat with no demolition, civil work typically takes 3–4 weeks. This is the noisiest, dustiest phase.

Weeks 7–12: Carpentry and Joinery

Wardrobes, kitchen (or modular kitchen installation), TV units, crockery units, false ceilings. The longest single phase — and the one most affected by material delays. Modular kitchen orders are placed at the design sign-off stage, timed to arrive when the kitchen phase begins.

Weeks 10–13: Painting

Putty, primer, and finish coats. Feature wall treatments (limewash, texture, wallpaper) follow the main painting. Painting happens after carpentry is substantially complete — doing it before saves a week and costs two weeks in paint damage from subsequent carpentry work.

Weeks 11–14: Electrical, Lighting, Plumbing Fixtures

Final electrical points, light fixture installation, switches and sockets. Bathroom fixture installation (taps, showers, sanitary ware). This phase runs in parallel with late carpentry and painting.

Weeks 13–17: Furniture, Curtains, and Accessories

Loose furniture delivery and placement. Custom curtains and blinds. Accessory and art placement. This is when the space starts looking finished.

Weeks 16–18: Snagging and Handover

A systematic walkthrough identifying every incomplete or substandard item: paint touch-ups, hardware adjustments, tile grouting, electrical issues. A written snag list is produced, addressed, and signed off before final handover.


What Makes Projects Run Late

Starting construction before the design is approved. The most common cause. When civil work begins "to save time" while 3D renders are still being revised, every mid-project design change becomes an expensive site-level change. The time saved is paid back with interest.

Material delays. Tiles ordered late. Modular kitchen lead time (3–4 weeks minimum from order) not factored into the schedule. Custom curtain fabric taking longer than quoted. These delays push handover by weeks without any fault in execution.

Too many decision-makers. Four people with sign-off authority and different opinions means decisions take 10 days that should take 1. Establish who has final approval before the project starts.

Scope changes after approval. "While we're at it, can we also do the study?" Mid-project additions reset the timeline proportionally.


How to Keep Your Project on Schedule

  • Approve 3D renders before any civil work begins
  • Order the modular kitchen at design sign-off, not when the kitchen phase starts
  • Make furniture selections before execution begins — not mid-project
  • Maintain 10–15% budget contingency so site surprises don't pause work
  • Have one designated decision-maker or a clear sign-off process

Frequently Asked Questions

Can a 2 BHK interior be done in under 10 weeks?

Technically yes — if scope is limited (kitchen + wardrobes + painting, no custom furniture), the flat is new possession with clean walls, and decisions are made within 24 hours. In practice, a complete 2 BHK with designed ceilings, bathroom upgrades, and furniture takes 12–16 weeks if done properly. "Done in 8 weeks" often means the painting happened before the carpentry and both had to be redone.

How long does the design phase take at Aura Foundry?

From first site visit to 3D render delivery: 2–3 weeks for a standard 2 BHK. Material sign-off adds 1–2 weeks. Total design phase: 3–5 weeks. Execution does not start until the design is approved — this protects your budget and the timeline.

What is the fastest way to get a finished interior?

Do the design work before possession day. If you know your possession date 2–3 months in advance, you can complete the full design phase — renders approved, materials selected, BOQ signed, contractors briefed — so execution starts the day you get access. This is exactly what we recommend for planned possessions.

Does Aura Foundry give a timeline commitment?

Yes. We produce a phase-by-phase project schedule at design sign-off with milestone dates. Timeline extensions require written approval and are triggered only by scope changes or supply issues outside our control.

How does a new-possession project compare in timeline to a renovation?

New-possession flats are faster: no demolition, clean walls, straightforward electrical. A complete new-possession 2 BHK runs 12–15 weeks. A full renovation of an occupied flat with demolition and waterproofing runs 16–24 weeks. Visit our services page to understand how we scope and price both types of project.

Ali Asgar Shabbir founder and lead designer Aura Foundry Interiors Undri Pune
Ali Asgar Shabbir
Founder & Lead Designer, Aura Foundry Interiors · Undri, Pune
Ready to Begin?

Book a Free Home Visit & Sketch

We visit your home, spend 60–90 minutes thinking about your space, and leave you with a hand-drawn concept sketch — free, no strings attached.

Book a Free Home Visit & SketchEstimate Your Budget
Call Us